This is a record of completed roading and infrastructure projects.
| Project Manager | |||
|---|---|---|---|
| Avenue Road West Sewer Rising Main & Pump Station | Ansonica Botha (HDC) | 8 November 2010 - 18 February 2011 | |
| Bridge Pa Water Supply | Derek Bensemann (MWH) | 28 May 2010 - 13 February 2011 | |
| Caroline Road & St Aubyn Street Intersection | Graeme McHattie (MWH) | 17 January 2011 - 11 November 2011 | |
| CBD Upgrade Project - Heretaunga Street West 300 Block | Derek Bensemann (MWH) | 30 May 2011 - 9 September 2011 | |
| Duke St | Derek Bensemann | 16 August 2010 - 13 May 2011 | |
| Eastbourne Street | Graeme Clarke | 26 November 2011 - 28 November 2011 | |
| Hawke's Bay Expressway - Construction of Southern Extension | Mike Wong (NZTA Liaison/Regional Project Manager) | 1 October 2009 - 24 February 2011 | |
| Holt Place Water Reconstruction | Ansonica Botha | 9 September 2011 - 14 November 2011 | |
| Karaitiana St stormwater | Graeme McHattie (MWH) | 10 May 2010 - 18 June 2010 | |
| Lumsden Road | Bryan Bell (HDC) | 6 November 2009 - 11 February 2011 | |
| Massey St | Graeme McHattie (MWH) | 1 March 2010 - 30 July 2010 | |
| Matahorua Road Seal Extension | Les Glock (HDC) | 1 October 2010 - 31 December 2010 | |
| Middle Road Rising Main & Breadalbane Road Pump Station | Nick Cottier | 21 February 2011 - 11 November 2011 | |
| Minor Safety work | Graeme McHattie (MWH) | 3 May 2010 - 28 May 2010 | |
| Nelson Street North - Brick Arch Sewer Rehabilitation | Ansonica Botha (HDC) | 31 January 2011 - 2 September 2011 | |
| Nelson Street North Road Reconstruction | Bryan Bell | 22 August 2011 - 23 December 2011 | |
| Nelson Street Sewer Ridermains | Ansonica Botha (HDC) | 25 September 2009 - 7 May 2010 | |
| Okaihau Road extension of seal | Les Glock (HDC) | 1 January 2011 - 31 May 2011 | |
| Percival & Evenden Road Intersection Construction | Nick Cottier | 2 August 2010 - 23 September 2011 | |
| Percival Road Stage 2 | Nick Cottier | 9 September 2011 - 16 December 2011 | |
| Richmond Road - Muddy Creek - Installation of Control Valve Chambers | Tony Dench (HDC) | 27 July 2009 - 24 July 2010 | |
| Road Works on Havelock Road and Havelock Bridge – 28 February – 2 March 2011 | Bill Blair | 28 February 2011 - 2 March 2011 | |
| Road Works on Rail Crossings – 18 – 28 February 2011 | Bill Blair | 14 February 2011 - 28 February 2011 | |
| Road Works on Stortford Lodge Roundabout | Bill Blair | 20 June 2011 - 15 July 2011 | |
| Second Coat & Maintenance Reseals | Les Glock (HDC) | 15 October 2009 - 24 June 2010 | |
| Taihape Road - Seal Extension | Les Glock (HDC) | 1 November 2010 - 28 February 2011 | |
| Tainui Drive, Awarua Crescent & Kenilworth Road - Watermain Construction | Derek Bensemann (MWH) | 5 July 2010 - 17 December 2010 | |
| Te Mata Road Inset Parking | Bryan Bell | 13 June 2011 - 9 September 2011 | |
| Tuki Tuki Road Widening and Road Rehabilitation | Les Glock (HDC) | 1 January 2011 - 31 May 2011 | |
| Urban, Plains and Rural Resealing Contract | Bill Blair (HDC) | 15 October 2010 - 15 April 2011 | |
| Wall Road | Derek Bensemann (MWH) | 16 August 2010 - 4 March 2011 | |
| Warren Street North - Pocket Park | Raoul Oosterkamp | 24 January 2011 - 31 March 2011 |