The local community, council, central government and contractor representatives gathered at Kererū Gorge on April 17 to mark the opening of a new culvert that will reconnect this key route to Hastings.
Kererū Gorge culvert was one of 19 bridges or large culverts lost in Cyclone Gabrielle, and is the second major permanent rebuild to be completed, following the reopening of Chrystal Culvert last year.
Flood damage from the cyclone resulted in the loss of about 50 metres of Kererū Road, the loss of the culvert drainage, and erosion of the stream to around eight metres below its previous level, making the gully about 18 metres deep.
The culvert that previously provided access over Whanaukini Stream has been replaced with a much larger permanent structure, in this case, a deep-fill multi-plate culvert and headwall. Following this, the road was rebuilt on top.
Designed and built by Stantec and Fulton Hogan Civil, the 15-metre-wide large arch culvert has been designed to raise the road, allowing for any future flood waters to pass underneath.
Hastings mayor Sandra Hazlehurst acknowledged Minister of Rural Affairs Mark Patterson and Tukituki MP Catherine Wedd who both attended this morning’s opening.
She said the news would be very welcome for the Maraekākaho and Kererū communities.
“Today was a huge celebration - a day we have been waiting for for a long time and many residents braved the walk down to join us.
“These residents have faced huge disruptions for a long time while this work has been undertaken.
“They’ve had long detours over Salisbury Road, and we appreciate their patience while this new structure has been built to a standard that will provide connection as well as ongoing resilience for the Kererū community.”
Councillor Marcus Buddo said the reopening of Kererū Gorge was a huge moment for the community.
“The last two years have been incredibly tough out here. The long detours via Salisbury Road have added hours to daily routines, impacting families, local businesses, and the school community. This reopening means Kererū can move forward from the damage of Cyclone Gabrielle, reconnected and resilient."
Further works below the road level will continue for about six more weeks to close out the project. Separate to this project, recovery works are continuing in the wider area including repairs to Olrig Bridge and slip stabilisation works.
8 May 2025
Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is
accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith.
Some of the information available in this site is from the New Zealand Public domain and supplied by relevant
government agencies. Hastings District Council cannot accept any liability for its accuracy or content.
Portions of the information and material on this site, including data, pages, documents, online
graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced
information or material is copyright to the respective provider.
© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz