Chrystal Twin Culvert on Matahorua Road was destroyed during Cyclone Gabrielle when flood waters sent a water tank downstream, blocking the culverts pipes and causing the water to build-up and encroach over the top of the road. The scouring out that followed eventually led to the road being completely washed away, creating a 35-metre gap and the community being cut-off.
In the immediate aftermath, Council’s roading team and contractors established 4 wheel-drive vehicle access upstream of the culvert site and by May 2023 a permanent solution was being investigated.
Today the twin culvert has been redesigned to be a 3.2 metre diameter single-culvert (which for context is only 1.1m smaller than the maximum legal height of a bus in New Zealand), with over 9 metres of stone strong blocks above it, up to the formation of Matahorua Road.
Crystal Culvert was officially opened on Friday 19 July 2024. Click here to read the media release about the Chrystal Culvert completion and opening.
In addition to Chrystal Culvert, there are a further four large culverts and thirteen bridges requiring complete rebuild.
The photos below show the scale and progress of the works up until 16 May 2024.
As well as the destruction of the Chrystal Twin Culvert, another five large culverts and thirteen bridges were destroyed. The focus now is on repair and restoration across the network. A programme of rebuilds and repairs has been developed with an estimated cost of $800 million. Due to the scale and complexity of the work required, this will likely take seven to ten years to be completed. Hastings District Council is prioritising work based on the vulnerability of roads to new weather events, levels of road use and the numbers of people affected.
Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is
accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith.
Some of the information available in this site is from the New Zealand Public domain and supplied by relevant
government agencies. Hastings District Council cannot accept any liability for its accuracy or content.
Portions of the information and material on this site, including data, pages, documents, online
graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced
information or material is copyright to the respective provider.
© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz