skip to main content

I want to...

Current filter:

Rubbish & Recycling Rubbish & Recycling

Dartmoor

Dartmoor

Key points for consideration

  • Design consideration: The detailed design of the option will be undertaken considering constructability, temporary access, safety in design, and residual operational risk management.
  • Longer spans and fewer columns: Whenever feasible, the bridges will incorporate longer spans and fewer columns in the water. This design approach aims to reduce the risk of flow blockage caused by debris and slash during flood events. However, earthquake resilience is still a major consideration.
  • Project timeline: The goal is to begin construction on a permanent replacement structure to the community by mid-to late 2025. 

Background

A new permanent bridge at Dartmoor is being constructed due to the catastrophic damage incurred to the existing structure during the Cyclone Gabrielle floods.  

During the cyclone, the bridge suffered a complete loss of all five bridge piers and seven spans.  In the immediate aftermath, Council’s roading team and contractors focussed on reconnecting communities and restoring access as quickly as possible.   

Dartmoor bridge

The site of the old bridge following Cyclone Gabrielle

A pedestrian bridge was installed at the end of March 2023, followed on 5 April by the temporary single-lane bridge now in use.  Some of the abutments remain in place and have been repaired and reused to support the temporary structure. The weight restrictions that apply to this bridge are 40T MAX at 10km/hr.

Dartmoor walking bridge

Pedestrian bridge

Feasibility study

A feasibility option study has been conducted, where potential solutions for Dartmoors bridge rebuild have been assessed. The feasibility report covered the condition of the original structure, damage caused by the Cyclone, and a feasibility assessment of multiple bridge and alignment options. The feasibility report was based on the following:

  • Geometrics 
  • Hydrology and climate effects 
  • Geotechnical/geology considerations 
  • Environmental considerations 
  • Constructability 
  • Cost 
  • Social impacts 
  • Other factors 

The proposed bridge will be a like-for-like replacement of the original structure (i.e. single lane bridge) with no cycle/walking provisions. Using minimum widths this equates to a bridge width of 5.1m. An overall bridge length of 104m is anticipated, with the increased bridge length accommodating the anticipated increase in flood levels.

Timeline

Feasibility study 
April 2024  
Mana whenua engagement and site investigations 
Late 2024 
Pre-application discussions with Hawke's Bay Regional Council and demolition 
Late 2024  
Draft methodology and construction drawings 
TBC 
Resource consent lodgement and processing 
TBC 
Packaged design delivery 
TBC 
Blessing ahead of works beginning 
TBC 
Works begin 
Second half of 2025 
Public open day 
TBC 
Blessing to open bridge 
 TBC 

 

Temporary Bridge construction

Temporary bridge under construction

Community meetings

Date Location Status
TBC TBC Pending

Details of any future community meetings will be added here, as and when confirmed.

Dartmoor temporary bridge openinga

Opening of the temporary bridge

Dartmoor limits

Limits over the temporary bridge

Loading...

Hastings District Council - Copyright © 2024 Hastings District Council

Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hastings District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz