Water infrastructure rolled out in Frimley

frimley pipe

Everything about the water infrastructure being installed in Frimley is large-scale – from the large diameter polyethylene pipes and the drill rig installing them, to a massive five-tonne pipe connector.

The pipe-laying is one of a number of significant projects in the Hastings Drinking Water Strategy either completed or underway, designed to improve drinking water safety and add capacity and resilience to the district’s water network.

Fulton Hogan has been contracted by Hastings District Council to complete the pipe installation, project managed by the company’s Three Waters Department manager Joe Symonds.

The pipes (500mm striped for raw water; 560mm and 630mm blue for drinking water) have been fusion welded together, doing away with traditional ‘joints’ that were a weak point in traditional pipe materials.  Using HDPE removes the risk of contaminants getting into the water system through joins, and the pipes have seismic resistance during earthquakes, giving the network resilience and strength.

A drill rig set up on Frimley Rd is boring the hole underground for the pipe, through which the pipe will be drawn back.  Using this technique means the need for long disruptive stretches of open trenching is avoided, minimising disturbance and reinstatement costs.

But the connections still require major excavations. The six-metre by six-metre hole at the intersection of Nottingley Rd and Frimley Rd is where a five-tonne ‘three-legged’ connection detail, measuring approximately four metres by four metres, will be installed. It will sit atop a 150-tonne concrete anchor block.

It will be moved into the hole in about two weeks, after which it will be connected to the new and existing pipes, the hole filled, and the road and roundabout reinstated. “All up, about another seven or eight weeks, depending on weather and ground conditions,” said Mr Symonds.

Further into the project, connections will also be required at the Frimley Rd intersection with Hapuku St, and where the pipes to and from the new water treatment and storage facility will join onto the water main.

Hastings District Council’s Frimley project manager Herman Wismeyer said the two main parts of the project – the pipe work and the storage and treatment facility – were proceeding well.

Construction of the treatment and storage facility got underway last week after the Resource Consent process was completed. “While the pipe work alone would have improved the network, by having both parts of the project we achieve those aims around water safety, capacity and resilience to a far greater level.”

Photo: The five-tonne, four-metre by four-metre, "connector detail" that will join the pipes on the corner of Nottingley Rd and Frimley Rd.

13 October 2020

Back to News

Loading...

Hastings District Council - Copyright © 2024 Hastings District Council

Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hastings District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz