All roads, culverts, and bridges have been inspected, and faults logged post Cyclone Gabrielle. The community can be assured that we are aware of the scale of damage, and the time, and cost to repair. At this stage, our estimated response and recovery cost is around $800M and will take 5-7 years to repair/rebuild. How this is funded will affect the timing of the rebuild and the development of any high-level programme.
We have work priorities based on road hierarchy and known higher-intensity farming routes. These do change as/when we receive information, and when road conditions change.
Our roading team are working with our maintenance contractors to implement the initial response activities to safeguard our vulnerable network. This work can be seen throughout the network now.
Our panel of consultants are busy with investigations and designs of the recovery aspects of bigger and more complex slips, bridge works, and culvert repairs on our road network, to develop the right and appropriate engineering solutions. These often require geotechnical investigations and surveying during the design phase prior to construction. Work is also well underway in this space, but the community may see small jobs being done while large sites seem to be left alone for now.
If a road user has a query about a site in particular, and there are reasons to elevate the site to a higher priority, we welcome them to call us on (06) 871 5000
For a map of road closures see below the table. Bridge table updated 25/08/2023.
Bridge | Investigation underway | Design underway | Site Clearance underway | Construction | Access Established | Loading |
Rissington | Complete | Complete | Complete | Open | 31 March |
(Class 1 / General Access traffic loading) 50 MAX 10kmh Vehicles need to reduce speed. |
Moeangiangi | Complete | Complete | Complete | Open | 13 June |
(Class 1 / General Access traffic loading) |
Whanawhana | Complete | Complete | Complete |
Open |
15 May |
(Class 1 / General Access traffic loading) 50 MAX 10kmh |
Ellis-Wallace | Complete | Complete | Complete |
Open |
11 August |
(Class 1 / General Access traffic loading) |
Mangatutu Low Level | Complete | Complete | Complete | Open | 15 June |
(Class 1 / General Access traffic loading) |
Arapaoanui Low Level | Complete | Complete | Complete | Open | 16 March | Access established. Permanent solution initiated for resilience. |
Mcvicars Culvert | Complete | Y | Y | Y | Temp Access Established | Permanent solution initiated for resilience |
Crystal Twin Culvert | Complete | Complete | Y | N | Access – 4x4 Established | Access for 4x4 just upstream of culvert while a permanent solution is underway |
Dartmoor | Complete | Complete | Complete | Open | 5 April |
Staging (Class 1 / General Access traffic loading) |
Waiohiki/Redclyffe | Complete | Complete | Complete | Open |
8 August |
30 km/hr max 8 tonne loading |
Matapiro | Complete | Y | N | N |
10 August temporary access established |
Options being confirmed for the permanent structure. |
Brookfield | Y | N | N | N | TBC | Resilience options for determining the outcome |
Darkeys Spur No.1 | Y | N | N | N | TBC | Large scale works required |
Puketapu | Complete | Y | N | N | TBC | Working through design |
Kereru Road Gorge Bridge | Complete | Y | Y | N | TBC | The permanent option is being explored |
Crownthorpe | Complete | Complete | Complete | Open |
Construction to continue, light vehicle access being established under traffic management. |
Light vehicles |
Follies | Complete | Complete | Complete | Open | 13 July | Permanent solution being explored while temporary access in place |
Weather, ground conditions and investigation outcomes will have an impact on the structures above. |
Below is a breakdown of short term solutions currently in place for those bridges lost during Cyclone Gabrielle:
Bailey bridges | Temporary crossings |
|
|
Temporary staging | No crossing currently |
|
|
This map shows road works and temporary road closures across Hastings. The map is interactive zoom in to view street names or click on an icon to find out more details about the work or event. You can also use the search function to find a particular road. To see a list of road works and closures in text format, click on the black arrow at the bottom centre of the map to display the list.
For all enquiries, please contact Hastings District Council. Public notices of temporary road closures can be found below the map.
There are currently no news articles.
Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is
accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith.
Some of the information available in this site is from the New Zealand Public domain and supplied by relevant
government agencies. Hastings District Council cannot accept any liability for its accuracy or content.
Portions of the information and material on this site, including data, pages, documents, online
graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced
information or material is copyright to the respective provider.
© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz