Of the approximately 13,000 total culverts across the HDC network that required inspection post-cyclone, more than 2,200 required cleaning/unblocking and almost as many again required at least some repair. This work is ongoing.
Total culverts |
Inspected |
Completed |
Require cleaning |
Require repair |
13,000 |
11,461 (88%) |
3,300 (25%) |
2,260 (17%) |
2,085 (16%) |
As well as the destruction of the thirteen bridges during Cyclone Gabrielle, five large culverts were destroyed. The focus now is on repair and restoration across the network. A programme of rebuilds and repairs has been developed with an estimated cost of $800 million. Due to the scale and complexity of the work required, this will likely take seven to ten years to be completed. Hastings District Council is prioritising work based on the vulnerability of roads to new weather events, levels of road use and the numbers of people affected.
Details of these culvert rebuilds will appear below as they are confirmed.
Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is
accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith.
Some of the information available in this site is from the New Zealand Public domain and supplied by relevant
government agencies. Hastings District Council cannot accept any liability for its accuracy or content.
Portions of the information and material on this site, including data, pages, documents, online
graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced
information or material is copyright to the respective provider.
© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz