skip to main content

I want to...

Current filter:

Rubbish & Recycling Rubbish & Recycling

Redclyffe/Waiohiki

Redclyffe Temp Bridge

Key points so far

  • Alignment significance:  The feasibility of bridge designs is intricately tied to the chosen alignment of the new bridge. Each alignment concept, will carry substantial implications, and guidance from mana whenua is of utmost importance, irrespective of the perspective taken.
  • Land acquisition: Alignments may require land acquisition as part of the project.
  • Co-design process: The bridge design will adhere to a co-design process, involving collaboration with mana whenua, in accordance with the Te Aranga design principles.
  • Flood scheme and network planning: The design of this bridge crossing is closely intertwined with the outcomes of the Hawke's Bay Regional Council (HBRC) future flood scheme and broader network planning efforts.
  • Shared ownership: It's important to note that this bridge is jointly owned by both Hastings District Council and Napier City Council.

Temporary staging bridge

A temporary staging bridge has been installed to replace the mid-section of the bridge that was washed away. The bridge ensures a safe passage for vehicles and pedestrians to cross the Tutaekuri River. The damaged mid-section of the Redclyffe Bridge, debris, silt, and obstacles were cleared from the riverbed to allow for the installation of staging. The temporary staging bridge is a 9-span steel beam and prestressed concrete deck structure. This bridge has been designed for a speed of 30km/h only.

Engineering and contractor teams are currently monitoring the existing structure either side of the staging bridge. This has resulted in a weight reduction of the overall bridge to be a maximum of 8 tonnes.

Community meetings

Details of community meetings will be added here, as and when confirmed.

Timeline

Karakia to bless the start of demolition April 2023 
Demolition of mid-section of the Bridge   April 2023
Karakia to bless the start the staging bridge construction June 2023 
Feasibility study July 2023
Mana whenua engagement and site investigations September 2023, ongoing
Pre-application discussions with Hawke's Bay Regional Council (HBRC) Mid-2025
Draft methodology and construction drawings TBC
Resource consent lodgement and processing Mid-2025
Packaged design delivery TBC
Blessing ahead of works beginning TBC
Works begin Late 2025
Public open day during works TBC
Blessing to open bridge Late 2027

Permanent bridge

A feasibility study is being conducted to assess and the engineering challenges linked to each potential bridge crossing locations. The study aims to propose bridge concepts that are achievable from an engineering standpoint. The feasibility report is based on the following:

  • Geometrics
  • Hydrology and climate effects
  • Geotechnical/geology considerations
  • Environmental considerations
  • Constructability
  • Cost
  • Social impacts
  • Other factors
Loading...

Hastings District Council - Copyright © 2024 Hastings District Council

Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hastings District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz