Post-cyclone roading repair and rebuild programme update

Matapiro Road crossing

With hundreds of slips cleared and culverts cleaned, and the detailed design of replacement bridges and major culverts well underway, the longer-term work plan for repairing Hastings’ cyclone-ravaged roading network is becoming clearer.

After focusing on installing temporary bridges and making urgent repairs to reconnect communities in the immediate aftermath of the cyclone, Council’s roading team and contractors had inspected the full 1640-kilometre network and simultaneously started on solutions for the major damage.

The result is a long list of rebuilds and repairs, estimated to take seven to eight years to complete.

As well as the 13 bridges that need to be completely rebuilt, another 40-plus need repairing, and there are five large and complex culvert rebuilds required.

Of Hastings’ 13,000 culverts, more than 2200 required cleaning and almost as many again required repair. This work is ongoing.

Puketapu Bridge will be the first permanent rebuild, aimed to be completed by the middle of 2025. This is expected to be followed by the rebuild of the Matapiro Bridge.

Across the whole bridge work programme, priorities could change depending on the likes of engineering advice, and the availability of contractors and materials.

So far more than 500 simpler slips had been cleared, another 211 larger slips assessed, and solutions for 20 of the most complex are being designed.

In terms of roading, more than 30 kilometres were damaged in the cyclone – the vast majority in the rural area – affecting both sealed and unsealed roads. 

Hastings deputy mayor and rural community board member Tania Kerr said given the scale of the damage, prioritisation of the repair and rebuild work was needed.

“Our contractors are working their way through the road repair and rebuild list, prioritising based on the level of vulnerability in new weather events, and the level of road use.”

Work on some of the larger culverts may take longer as materials are sourced overseas and have long lead times because of sea freight/shipping.

“As well as focusing on the rebuild, the team is continuing with normal maintenance work. Drains are being cleared and sprayed out, and trees are being trimmed off the road corridor,” Mrs Kerr said.

Mrs Kerr said the team of engineers and contractors continued to work at pace recognising the importance of the rural network to the community to be able to continue to access work, school, family and fun.

More information on the roading recovery can be found here.

19 December 2023

Back to Archive

Loading...

Hastings District Council - Copyright © 2024 Hastings District Council

Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hastings District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz