Current filter:
Photo: Peter Scott, Above Hawke's Bay
In February 2023, Cyclone Gabrielle destroyed about 50 metres of Kererū Road, washed away its culvert drainage, and eroded the streambed to 8 metres below its original level —creating an 18-metre-deep gully.
Kererū Gorge as it appeared in September 2021
Kererū Gorge was one of 18 bridges or culverts lost in the cyclone, cutting off a key route into Hastings. Residents have faced long detours via Salisbury Road, disrupting connections with schools and neighbours. Unlike other damaged sites, an interim fix here would have cost nearly as much as a permanent one, making it a priority for early reconstruction.
A feasibility study recommended a 15-metre-wide segmented culvert as the best long-term solution. Instead of a bridge, the large arch culvert was designed to raise the road while allowing floodwaters to pass. Precast concrete panels were used to speed up construction.
In November 2024, a structural evaluation found that weak ground conditions required deeper foundations. To reduce weight, expanded polystyrene blocks with extra steel reinforcement were used. As a result, the road was not able to be reopened by Christmas as planned but will open by Easter 2025.
Progress update (March 2025)
The structure is nearing completion with pavement (road surface) and drainage works underway. Over the next month, shotcreting (spray concrete) for tie-ins, stream diversion, revegetation, final surfacing, guardrail installation, line marking, and signage installation are all planned.
While the road will reopen to the public on Thursday 17 April, further works below road level will continue for approximately 6 more weeks to close out the project.
Feasibility study | Completed December 2023 |
Site preparation for construction | From 19 February 2024 |
Detailed design | February 2024 |
Mana whenua engagement, community engagement | February 2024 |
Works begin | Mid-March 2024 |
Official opening | 17 April 2025 |
Date | Location | Status | Presentations |
Community meeting Wednesday 12 February 2024. 6:00pm-8:00pm |
Kererū Hall |
COMPLETE | Presentation |
Site tour Saturday 23 November 2024, 10:15am-10:45am |
Kererū Gorge construction site | COMPLETE | |
Community meeting Monday 26 February 2024, 6:00pm-7:30pm |
Kererū Hall | Stantec Presentation |
Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is
accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith.
Some of the information available in this site is from the New Zealand Public domain and supplied by relevant
government agencies. Hastings District Council cannot accept any liability for its accuracy or content.
Portions of the information and material on this site, including data, pages, documents, online
graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced
information or material is copyright to the respective provider.
© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz