Hastings-Havelock North water main project news

 

Final stages of pipe project, temporary bridge closure

The Crosses Rd bridge is to be closed for one day next week as part of the final stages of the Hastings to Havelock North water main project.

16 November 2018

read more »

Crosses Rd bridge

Hastings to Havelock North Water Main Project - October Update

It's taken time, but this project is nearly there! Thank you for your patience - there are just a few last jobs to be completed:

22 October 2018

read more »

Pipe Project2

New trees planted on Napier Road

With the roadworks in Napier Road nearly complete, a number of people gathered today to plant 21 new trees along the central median strip.

17 October 2018

read more »

napier rd trees

Hastings to Havelock North Water Main Project - July Update

Hastings District Council understands the impact and disruption roadworks have on everyone. Full reinstatement of the roads affected by this project will be completed as fast as possible as the project reaches completion. Thank you for your ongoing patience whilst this project is completed.

1 July 2018

read more »

Pipe Project

Tree removal for new water main

About 30 trees along Napier Rd will be removed over the next fortnight, in preparation for the laying of the Havelock North section of the new Hastings to Havelock North water main.

22 May 2018

read more »

KDrive

Pipe progress and road closures

There are clear signs of progress on the project to install a new water main between Hastings and Havelock North, with more than 30 per cent of the 4.8km length in the ground. In Crosses Rd there is just 200m left to go and the road re-sealing team has started work behind them.

16 May 2018

read more »

IMG 2898 Small

Pipe progress; traffic management changes

The installation of the critical new water main between Hastings and Havelock North is continuing at a good pace with nearly a quarter of the water pipe in place. So far, 1000 metres of pipe has been laid across the four work sites.

20 April 2018

read more »

H Hn pipe st aubyn

Hundreds of metres of pipe already in

More than 200m of the new main water pipe has been laid at two locations since site work on the new Hastings to Havelock North main water pipe started on March 7. In Howard St 120m had been laid by Tuesday (March 20), heading towards central Hastings; in Crosses Rd 136m had been laid.

23 March 2018

read more »

h hn pipes3 Small

Ground-breaking for water main next week

The construction of a new Hastings to Havelock North water main gets underway next week, after contractors March Construction took over the site on Wednesday (February 28). Traffic management is being set up over the next few days ahead of the start of physical work, expected to get underway on Monday.

1 March 2018

read more »

water main Small

Route for major water main announced

One of the largest projects included in the Hastings District Council’s water strategy is about to get underway. The route for the new mains water pipe between Hastings and Havelock North has been finalised and a contractor is expected to be selected this month, after which work will start.

5 February 2018

read more »

Hastings Havelock Map

38 page views for the last 30 days

Share this page
Share on Facebook Share on Twitter Share on Google+ Share on LinkedIn Share by Email

Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hastings District Council cannot accept any liability for its accuracy or content. Portions of the Hastings District Council information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hastings District Council - www.hastingsdc.govt.nz / +64 6 838 7309 / Fax: +64 6 838 8874