Key points for consideration
A feasibility study is being conducted to assess and the engineering challenges linked to each potential bridge crossing locations. The study aims to propose bridge concepts that are achievable from an engineering standpoint. The feasibility report is based on the following:
Bailey bridge construction | February - May 2023 |
Karakia to bless the opening of the bailey bridge | May 2023 |
Feasibility study | September 2023 |
Mana whenua engagement, community engagement and site investigations | Mid-2023 |
Pre-application discussions with Hawke's Bay Regional Council (HBRC) | Late-2023 |
Removal of damaged structures still in the waterway | 15 April to mid-May 2024 |
Draft methodology and construction drawings | TBC |
Resource consent lodgement and processing | TBC |
Packaged design delivery | TBC |
Blessing ahead of works beginning | TBC |
Works begin | TBC |
Blessing to open bridge | TBC |
Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is
accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith.
Some of the information available in this site is from the New Zealand Public domain and supplied by relevant
government agencies. Hastings District Council cannot accept any liability for its accuracy or content.
Portions of the information and material on this site, including data, pages, documents, online
graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced
information or material is copyright to the respective provider.
© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz