skip to main content

I want to...

Current filter:

Rubbish & Recycling Rubbish & Recycling

Matapiro

Matapiro Bridge Feb

Project update (8 April, 2025)

We are pleased to share that vehicles can now drive over the Matapiro Bridge with temporary traffic controls in place through the site. A huge thank you to the community for their co-operation during the recent closure of Matapiro Road, which significantly sped up the construction timeline.

While there is still some work to do over the coming months, including completing the bridge surfacing, finishing scour works, removing the temporary crossing, and some minor tidying-up, the project remains on track for completion by the end of June. An official opening and celebration will then occur with a formal karakia and a Matapiro Pou unveiling.

Key points for consideration

  • Temporary crossing challenges: A temporary crossing has provided short-term relief but is vulnerable during significant rainfall events.
  • Alignment choice: Reconstructing the bridge on the existing alignment is deemed the optimal approach to meet the required timeline and stakeholder expectations.
  • Environmental considerations: The impact on fish spawning in the river is being carefully considered throughout the project's planning.
  • Project timeline: The goal is to deliver a permanent replacement structure by mid-to late 2025.
  • Bridge design: A two lane bridge with no shared user path has been confirmed as the preferred option for Matapiro Bridge replacement.

Background

Matapiro Bridge was a three-span concrete T-beam bridge with a concrete deck, constructed in approximately 1955. The substructure included two piers consisting of four slender square columns, a pier and two solid wall abutments.

Bridge length 37.2m
Span arrangement  11.3m, 14.6m, 11.3m
Bridge width 8.0m
Carriageway width 7.3m
Lane arrangement  2/3.65m incl. shoulders

Following the destruction of the concrete bridge during Cyclone Gabrielle, a temporary culverted crossing was deemed an acceptable solution. 

Design considerations

  • Two lanes
  • Increased height due to flood risk
  • Increased pile depth
  • Earthquake considerations
  • Best practice engineering guidelines and standards

Community meetings

Date Time Location Status
Tuesday 26 March 2024 6:00pm-7:30pm Matapiro Hall

COMPLETE

Click here to view the meeting presentation.

Timeline

Karakia to bless the demolition of the damaged bridge June 2023
Feasibility study completed July 2023
Demolition of damaged bridge June – July 2023
Mana whenua engagement September 2023, ongoing
Temporary crossing works completed September 2023
Geotechnical testing on site  September 2023
Ecological and cultural impact assessments December 2023– February 2024
Community meeting Tuesday 26 March, 6pm-7:30pm, Matapiro Hall
Pre-application discussions with Hawke's Bay Regional Council (HBRC) January – February 2024
Draft methodology and construction drawings TBC
Tender process to confirm contractor  March - August 2024
Resource consent lodgement and processing February-March 2024
Packaged design delivery TBC
Blessing ahead of works beginning TBC
Works begin Late 2024/early 2025
Site is trafficable 6 April 2025
Blessing to open bridge End of June 2025

Matapiro Temporary Crossing

Temporary crossing as at 4/12/2023

Newsletters

Loading...

Hastings District Council - Copyright © 2025 Hastings District Council

Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hastings District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz