skip to main content

I want to...

Current filter:

Rubbish & Recycling Rubbish & Recycling

Matapiro

Matapiro Bridge

Key points for consideration

  • Temporary crossing challenges: A temporary crossing has provided short-term relief but is vulnerable during significant rainfall events.
  • Alignment choice: Reconstructing the bridge on the existing alignment is deemed the optimal approach to meet the required timeline and stakeholder expectations.
  • Environmental considerations: The impact on fish spawning in the river is being carefully considered throughout the project's planning.
  • Project timeline: The goal is to deliver a permanent replacement structure by mid-to late 2025.
  • Bridge design: A two lane bridge with no shared user path has been confirmed as the preferred option for Matapiro Bridge replacement.

Background

Matapiro Bridge was a three-span concrete T-beam bridge with a concrete deck, constructed in approximately 1955. The substructure included two piers consisting of four slender square columns, a pier and two solid wall abutments.

Bridge length 37.2m
Span arrangement  11.3m, 14.6m, 11.3m
Bridge width 8.0m
Carriageway width 7.3m
Lane arrangement  2/3.65m incl. shoulders

Following the destruction of the concrete bridge during Cyclone Gabrielle, a temporary culverted crossing was deemed an acceptable solution. 

Demolition

  • Demolition is complete
  • Crushed concrete material from demolition is available to be reused in the rebuild to minimise environmental impacts
  • Steel material has been recycled locally

Matapiro Bridge demolition

Design considerations

  • Two lanes
  • Increased height due to flood risk
  • Increased pile depth
  • Earthquake considerations
  • Best practice engineering guidelines and standards

Community meetings

Date Time Location Status
Tuesday 26 March 6:00pm-7:30pm Matapiro Hall

COMPLETE

Click here to view the meeting presentation.

Newsletters

Timeline

Karakia to bless the demolition of the damaged bridge June 2023
Feasibility study completed July 2023
Demolition of damaged bridge June – July 2023
Mana whenua engagement September 2023, ongoing
Temporary crossing works completed September 2023
Geotechnical testing on site  September 2023
Ecological and cultural impact assessments December 2023– February 2024
Community meeting Tuesday 26 March, 6pm-7:30pm, Matapiro Hall
Pre-application discussions with Hawke's Bay Regional Council (HBRC) January – February 2024
Draft methodology and construction drawings TBC
Tender process to confirm contractor  March - August 2024
Resource consent lodgement and processing February-March 2024
Packaged design delivery TBC
Blessing ahead of works beginning TBC
Works begin Late 2024/early 2025
Public open day TBC
Blessing to open bridge Mid-2025

Works completed to date

A feasibility study has been conducted to assess and the engineering challenges linked to each potential bridge crossing location. The study aims to propose bridge concepts that are achievable from an engineering standpoint. The feasibility report is based on the following:

  • Geometrics
  • Hydrology and climate effects
  • Geotechnical/geology considerations
  • Environmental considerations
  • Constructability
  • Cost
  • Social impacts
  • Other factors

The team have also completed/in the process for completing:

  • Ecological impact assessment
  • Archaeological assessment
  • Land contamination testing
  • Geotechnical borehole testing
Matapiro Temporary Crossing

Temporary crossing as at 4/12/2023

Frequently asked questions

Showing search results for ""

Current filter:

Matapiro Bridge

Matapiro Bridge was destroyed during Cyclone Gabrielle and the damaged bridge was demolished in June and July 2023. A temporary crossing was established in August 2023. 

A series of necessary investigations and consultation necessary to inform a detailed design have been completed. These included: 

  • Demolition
  • Feasibility alignment reports 
  • Options reports
  • Ecology assessments 
  • Archaeology report 
  • Land contamination testing and reporting 
  • Cultural impact assessment
  • Mana Whenua engagement
  • Landowner agreements
  • Geotechnical testing 
  • Survey investigations
  • Hydrology and hydraulics reports
  • Economic evaluations
  • Geometric investigations
  • Resource consent discussions

The outcome of these investigations is that the previous alignment has been identified as the most resilient location.  The new bridge will be built on the same alignment. It will be longer, higher and have fewer piles in the waterway, making it more resilient to future weather events.

No. The previous bridge was built in 1955. It was a 37.2m long 3 span concrete bridge.

Old Matapiro Bridge

The design of the new bridge is out for tender currently, but it will need to be compliant with modern best practice standards. This means it will be a minimum of 60m long, have 2 lanes and a maximum of 2 spans.

This will increase the resilience to future extreme weather and earthquake risk.

Example of new bridge

Example of what the new Matapiro Bridge could look like.

The tender for design and build of the new bridge is currently out with local bridge contractors. Investigations have informed the replacement bridge requirements which are:

  • To be rebuilt on the same alignment
  • Have 2 lanes of traffic
  • Maximum of 2 spans
  • Minimum length of 60m
  • Designed to 1.2m freeboard for flooding including climate change
  • Meet all modern best practice standards

Over the coming weeks engineers will be completing regular checks on the temporary structure.

Geotechnical testing for earthquake requirements is scheduled for the 10th of  April 2024.

We expect the tender to be awarded by September 2024, and construction to be complete by September 2025.

Site establishment will likely begin in late 2024.

With investigation work largely complete and more on the ground work underway and imminent, there will be increased project communications. Click here to sign up to the Kaweka Ward newsletter (which will include updates on the Matapiro Bridge).

Whanawhana Bridge

A Bailey Bridge in place at Whanawhana is providing general access traffic loading with heavy vehicle traffic up to 50tonnes permitted at 10km/hr maximum speeds.

Whanawhana bailey bridge

Whanawhana bailey bridge

Because this access is in place, priority of bridge rebuilds is going to other areas which do not have temporary access or where this is limited, like Puketapu, Kereru and Matapiro. Therefore, fewer investigations have been completed at Whanawhana and the rebuild is scheduled in the outer years of the 7-10 year recovery programme.

Engineers are completing regular checks on the temporary structure. 

Demolition of the old structure will be completed by 1 May 2024.

There will be geotechnical testing onsite in the next 4-6 weeks

The same process will be followed as was the case for Matapiro, and the new bridge will be required to meet modern design standards. It will be longer and taller than the previous bridge and have fewer piles in the water for increased resilience. The rebuild is scheduled in the outer years of the 7-10 year recovery programme.

Matapiro Slip Repairs

Across the district, more than 800 slips were caused by the cyclone.

All 590 less complex slips have now been cleared and repairs made. There are a further 212 larger and more complex slips requiring investigation and major construction to repair. Almost half (102) of these are in the Kaweka Ward.

Twenty-six of these ‘tier 2 and 3’ slips are on Crownthorpe Settlement Road (6), Taihape Road (11) and Whanawhana Road – see the map below. Due to the scale and complexity of the damage, design and construction of the repairs to the road and associated drainage requires engineering expertise and resource consents. A prioritised programme of works has been developed to repair these, with priority going to maintaining access for isolated communities and key arterial routes. Council are working through the consenting and procurement process with NZTA Waka Kotahi and partners. As investigations and engineering designs are completed, contractors are being engaged to begin construction at each site.

Matapiro Slip repairs

 

Taihape Road Slip Repairs

There are 11 large and complex slip sites still present along Taihape Road that require engineering solutions. Sites have been secured and stabilised. Design has been completed for nine of these sites, and is nearing completion for the final two.

Tenders for the construction of the repair to these slips will be going out to market in the next few weeks.

We expect construction of these sites to be underway between July 2024 and June 2025. The exact construction dates will be confirmed after the tender for construction has been awarded.

Taihape Road slip site

Taihape Road slip site

Taihape Road Bridge Repairs

In addition to the eighteen bridges and large culverts destroyed by the cyclone, eighty have suffered significant damage requiring large and complex repairs.

Ten of these are along Taihape Road. Initially, priority was on re-establishing access for at least one lane of traffic through this important connecting route. Temporary repairs were done to stabilise damaged bridges and they are being regularly monitored and assessed.

Designs are being finalised for the bridges and, with the exception of Blacks Bridge, permanent repairs are expected to be completed by the end of 2025.

Damage to Pukehamoamoa bridge 1

Temporary repair to Pukehamoamoa bridge

Bridge 244 – Pukehamoamoa. Images of damage after the cyclone and temporary repair. Permanent repair expected to be complete by the end of 2024.

No. The funding only allows us to reinstate the bridges back to their pre-cyclone state, like for like. 

Matapiro Road Maintenance

The condition of the road has been reviewed and assessed. Parts of it have been significantly damaged by the extraordinary volume of heavy trucks using the road in response to Cyclone Gabrielle. These sites have been assessed as being damaged beyond resealing and require the whole road to be ripped up, strengthened, and rebuilt. 

There are two sections of Matapiro Road that HDC have designed for Area Wide Pavement Treatment. The first section runs from Taihape Road to just past Crownthorpe Settlement Road, and the other is from approximately RAPID 800 to the ACM quarry. 

Pavement testing and new pavement designs have just been finalised. Council is in the process of seeking release of funding to enable us to fast track these projects as part of Cyclone Gabrielle works. The extraordinary volume of heavy trucks responding to the effects of the cyclone, combined with higher future forecasted aggregate cartage as part of recovery works provides a strong case for us to enable these works through the cyclone response funding streams.  

Physical works is likely to start after the 2024 winter. This will mean more routine maintenance will be needed until the works start. 

We continue to encourage the community to report any issues requiring maintenance either by phone (06) 871 5000 or via the Hastings District Council website.  Doing so, will ensure this work is allocated to available contractors as a matter of priority. In the event of road accidents or dangerous driving, please report these to Police in the first instance.

Recent repairs on the likes of Otamauri, Crownthorpe and Crownthorpe Settlement Roads are all in advance of planned resealing works. We undertake periodic maintenance like this prior to resealing as we want to minimise the intervention once we reseal a road. The Matapiro sites are beyond resealing and require the whole road to be ripped up, strengthened, and rebuilt.

Matapiro Road between ACM and the bridge (and surrounds) has been significantly damaged as a result on the cyclone. There were oversized, and overweight trucks used on the road in the immediate response phase which has resulted in a significant reduction in remaining useful life of the road, and many parts have had temporary repairs done, with more repairs required until the bridge is rebuilt.

The mode of failure along the stretch between Rapid 800-1000 indicates that a lack of pavement depth is a major factor of the problems we are seeing. Stabilising this stretch without strengthening the road (by rebuilding the pavement to an increased depth) would result in early failure still.

The increase in current and future aggregate cartage necessitates earlier than expected large scale rebuild.

This is a significant project that is outside of the normal programme of work and requires the release of funding and scheduling of a rebuild.  

Council is in the process of seeking release of funding to enable us to fast track these projects as part of Cyclone Gabrielle works. The extraordinary volume of heavy trucks responding to the effects of the cyclone, combined with higher future forecasted aggregate cartage as part of recovery works provides a strong case for us to enable these works through the cyclone response funding streams.

Physical works is likely to start after the 2024 winter. This will mean more routine maintenance will be needed until the works start.

We continue to encourage the community to report any issues requiring maintenance either by phone (06) 871 5000 or via the Hastings District Council website.  Doing so, will ensure this work is allocated to available contractors as a matter of priority. In the event of road accidents or dangerous driving, please report these to Police in the first instance.

Whanawhana Road Maintenance

A request for pothole repairs has been sent to our maintenance contractor. All slips across the district have been prioritised, as the slips on Whanawhana Road will be designed, and repaired in due course. At this time we cannot give a certain date when the slips will be remediated.

We continue to encourage the community to report any issues requiring maintenance either by phone (06) 871 5000 or via the Hastings District Council website. Doing so, will ensure this work is allocated to available contractors as a matter of priority. In the event of road accidents or dangerous driving, please report these to Police in the first instance.

Omapere Bridge

A request for pothole repairs has been sent to our maintenance contractor. The bridge engineers will also be out in the first week of April and will assess the approach.
For the permanent fix for this bridge, the earliest this will start is September. Options have been developed and the engineering designs should be developed in May, after which the construction contract will be awarded.

Flooding Resilience

Hawke’s Bay Regional Council are leading a flood resilience project. Currently investigations are underway for potential solutions to improve the flood resilience in the area which could include stopbanking, drainage and streams work.

Flooding resilience

Hydrological modelling is underway. A site visit over the area happened on Wednesday 27 March.

More information and updates about the project can be found here.

Loading...

Hastings District Council - Copyright © 2024 Hastings District Council

Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hastings District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz