Current filter:
We are pleased to share that vehicles can now drive over the Matapiro Bridge with temporary traffic controls in place through the site. A huge thank you to the community for their co-operation during the recent closure of Matapiro Road, which significantly sped up the construction timeline.
While there is still some work to do over the coming months, including completing the bridge surfacing, finishing scour works, removing the temporary crossing, and some minor tidying-up, the project remains on track for completion by the end of June. An official opening and celebration will then occur with a formal karakia and a Matapiro Pou unveiling.
Matapiro Bridge was a three-span concrete T-beam bridge with a concrete deck, constructed in approximately 1955. The substructure included two piers consisting of four slender square columns, a pier and two solid wall abutments.
Bridge length | 37.2m |
Span arrangement | 11.3m, 14.6m, 11.3m |
Bridge width | 8.0m |
Carriageway width | 7.3m |
Lane arrangement | 2/3.65m incl. shoulders |
Following the destruction of the concrete bridge during Cyclone Gabrielle, a temporary culverted crossing was deemed an acceptable solution.
Date | Time | Location | Status |
Tuesday 26 March 2024 | 6:00pm-7:30pm | Matapiro Hall |
Karakia to bless the demolition of the damaged bridge | June 2023 |
Feasibility study completed | July 2023 |
Demolition of damaged bridge | June – July 2023 |
Mana whenua engagement | September 2023, ongoing |
Temporary crossing works completed | September 2023 |
Geotechnical testing on site | September 2023 |
Ecological and cultural impact assessments | December 2023– February 2024 |
Community meeting | Tuesday 26 March, 6pm-7:30pm, Matapiro Hall |
Pre-application discussions with Hawke's Bay Regional Council (HBRC) | January – February 2024 |
Draft methodology and construction drawings | TBC |
Tender process to confirm contractor | March - August 2024 |
Resource consent lodgement and processing | February-March 2024 |
Packaged design delivery | TBC |
Blessing ahead of works beginning | TBC |
Works begin | Late 2024/early 2025 |
Site is trafficable | 6 April 2025 |
Blessing to open bridge | End of June 2025 |
Temporary crossing as at 4/12/2023
Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is
accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith.
Some of the information available in this site is from the New Zealand Public domain and supplied by relevant
government agencies. Hastings District Council cannot accept any liability for its accuracy or content.
Portions of the information and material on this site, including data, pages, documents, online
graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced
information or material is copyright to the respective provider.
© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz