Water Service Connections
The Council provides stormwater, sewer and water connections. A connection is the piece of pipe that joins your property to the various networks. Applications for a connection are handled by the Asset Management group at the Council.
The Council’s underground services maintenance contractor is the only party, authorised to install new connections.
The cost of a new connection includes the physical works cost and a development levy fee.
The physical works cost is dependent on the length of pipeline between the service main and the boundary.
To apply for a service connection, complete the application form referenced in the related documents link below.
Contact
For more information contact council for cost details.
Water
Water Fees and Charges approved for 1 July 2017 to 30 June 2018.
All fees and charges are inclusive of GST (except as noted *).
| Water Connections | Fee (incl GST) |
| Processing Application | |
| Initial Application | $29.88 |
| Inspection and Auditing | $119.49 |
| Total Fee | $149.37 |
| Connection to HDC Water Network | |
| <100mm main | $221.70 |
| 100mm main | $217.59 |
| 150mm main | $266.47 |
| 200mm main | $304.89 |
| >200mm main | $734.09 |