Hundreds of metres of pipe already in

More than 200m of the new main water pipe has been laid at two locations since site work on the new Hastings to Havelock North main water pipe started on March 7.

In Howard St 120m had been laid by Tuesday (March 20), heading towards central Hastings; in Crosses Rd 136m had been laid.

Hastings mayor Sandra Hazlehurst said the critical main water pipe, linking Havelock North into the Hastings water supply, would enable Council to discontinue supplying water from the Brookvale bore field. “This is a very important project that will be a major contributor to increasing the safety, resilience and capacity of our drinking water supply. It is a major project which sits within our Drinking Water Strategy.

“Every aspect of our approach has been under review since the 2016 Havelock North water contamination, particularly including new information relating to the aquifer, which we rely on for our water supply. We have taken the learnings from all the work that has been undertaken since then, both within Council and externally, and used that to build this new strategy.”

“The laying of more than 200 metres of pipe is excellent progress,” said Hastings District councillor and works and services committee chairman Kevin Watkins. “This is a significant major project and we are very pleased that the construction is working very smoothly.”

A third work site St George’s Rd is getting underway. Waste water work that is being undertaken in conjunction with the water main project in the Park Rd to Howard St area is also expected to get underway in the next few days, as soon as the contractors doing this work are freed up from another project, said Mr Watkins.

Some fine-tuning around vehicle management had been put in place, with traffic signals controlling traffic overnight in the areas where roads had been reduced to single lane. Once work in Crosses Rd is further from the Karamu Stream bridge, traffic lights will be trialled during the day. They are also being considered for Howard St outside of school opening and closing times. “At all times, our highest priorities are safety around the site and the smooth flow of traffic. As changes are made they will be carefully monitored to ensure they are achieving those aims,” said Mr Watkins.

The laying of the new Hastings to Havelock North water main was one of a number of actions within the Drinking Water Strategy that were already underway, Mrs Hazlehurst said.

Others included the raising of bore heads to above ground (which has been completed), the fitting of UV filter treatment to all water supplies, investigating a new water source in the Whakatu/Tomoana area, and adding further enhancements to all the smaller water supplies. 

23 May 2018

Back to Archive

Loading...

Hastings District Council - Copyright © 2024 Hastings District Council

Disclaimers and Copyright
While every endeavour has been taken by the Hastings District Council to ensure that the information on this website is accurate and up to date, Hastings District Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hastings District Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hastings District Council - / +64 6 871 5000 / customerservice@hdc.govt.nz